(1) An insured or the claimant shall give notice to the insurer of any loss arising under contract of insurance at the earliest or within such extended time as may be allowed by the insurer.
On receipt of such a communication, a general insurer shall respond immediately and give clear indication to the insured on the procedures that he should follow. In cases where a surveyor has to be appointed for assessing a loss/ claim, it shall be so done within 72 hours of the receipt of intimation from the insured.
(2) Where the insured is unable to furnish all the particulars required by the surveyor or where the surveyor does not receive the full cooperation of the insured, the insurer or the surveyor as the case may be, shall inform in writing the insured about the delay that may result in the assessment of the claim.
The surveyor shall be subjected to the code of conduct laid down by the Authority while assessing the loss, and shall communicate his findings to the insurer within 30 days of his appointment with a copy of the report being furnished to the insured, if he so desires. Where, in special circumstances of the case, either due to its special and complicated nature, the surveyor shall under intimation to the insured, seek an extension from the insurer for submission of his report.
In no case shall a surveyor take more than six months from the date of his appointment to furnish his report.
(3) If an insurer, on the receipt of a survey report, finds that it is incomplete in any respect, he shall require the surveyor under intimation to the insured, to furnish an additional report on certain specific issues as may be required by the insurer. Such a request may be made by the insurer within 15 days of the receipt of the original survey report.Â
Provided that the facility of calling for an additional report by the insurer shall not be resorted to more than once in the case of a claim.Â
(4) The surveyor on receipt of this communication shall furnish an additional report within three weeks of the date of receipt of communication from the insurer.
(5) On receipt of the survey report or the additional survey report, as the case may be, an insurer shall within a period of 30 days offer a settlement of the claim to the insured. If the insurer, for any reasons to be recorded in writing and communicated to the insured, decides to reject a claim under the policy, it shall do so within a period of 30 days from the receipt of the survey report or the additional survey report, as the case may be.
(6) Upon acceptance of an offer of settlement as stated in sub-regulation (5) by the insured, the payment of the amount due shall be made within 7 days from the date of acceptance of the offer by the insured. In the cases of delay in the payment, the insurer shall be liable to pay interest at a rate which is 2% above the bank rate prevalent at the beginning of the financial year in which the claim is reviewed by it.